新足迹

 找回密码
 注册

精华好帖回顾

· 定下心了,发个帖子,给找工作的同志们做个参考 (2006-7-22) wzline · 最近的忙碌 (2005-9-14) leeshine
· 和基友的圣诞跨年日本之旅 (2014-11-15) shintaku · 写给即将踏上澳洲土地的朋友们 (1)(看过的朋友就不要费神近来了) (2004-12-20) spirit1
Advertisement
Advertisement
12
返回列表 发新帖
楼主:Gelen

[修房建房] 盖房子的请进:建房顺序排列,答对加20分 [复制链接]

发表于 2011-3-11 09:45 |显示全部楼层
此文章由 ukbing 原创或转贴,不代表本站立场和观点,版权归 oursteps.com.au 和作者 ukbing 所有!转贴必须注明作者、出处和本声明,并保持内容完整
1.        Prepare and clear the site.
2.        Construct footings/subfloor.
3.        Construct floor.
4.        Erect walls and roof structure.
5.        Install roof covering and roof drainage.
6.        Install Windows.
7.        Install service pipes, wires, windows, etc.
8.        Install external cladding, doors etc.
9.        Install internal linings.
10.        Install joinery and cabinets.
11.        Apply finishing coverings (paint, tiles, carpets, etc.).
12.        Install and connect service outlets/fixtures.
13.        Clean up and move in.
Advertisement
Advertisement

发表于 2011-3-12 21:28 |显示全部楼层
此文章由 XR8 原创或转贴,不代表本站立场和观点,版权归 oursteps.com.au 和作者 XR8 所有!转贴必须注明作者、出处和本声明,并保持内容完整
还不加分?
快快快
每人20分,不带赖皮的

发表于 2011-3-26 21:00 |显示全部楼层
此文章由 bourne126 原创或转贴,不代表本站立场和观点,版权归 oursteps.com.au 和作者 bourne126 所有!转贴必须注明作者、出处和本声明,并保持内容完整
1.Prepare and clear the site.
2.Construct footings/subfloor.
3.Construct floor.
4.Erect walls and roof structure.
5.Install Windows.
6.Install roof covering and roof drainage.
7.Install service pipes, wires, windows, etc.
8.Install external cladding, doors etc.
9.Install internal linings.
10.Install joinery and cabinets.
11.Install and connect service outlets/fixtures.
12.Apply finishing coverings (paint, tiles, carpets, etc.).
13.Clean up and move in.

发表回复

您需要登录后才可以回帖 登录 | 注册

本版积分规则

Advertisement
Advertisement
返回顶部