最后从albany35改到了nevada35,base price比albany的还要便宜了$2k。。。然后过了几天收到nigel的比原来的quote贵了$1.2k的fixed package quote。主要是site cost,council和developer requirement这些比原来的quote要高了。。。
Site Cost:
Footing adjustment - Inc
Additional reo due to fill - Inc
Angle of repose allowance - Bored piers - Inc
Shadecloth protection to Double Storey homes - Inc
Site Fall/Earthworks - Scrape
Retaining walls - N/A
S-Flashing to Garage - Inc
Material Handling - N/A
Additional Connections allowance - N/A
Rock removal - N/A
SUBTOTAL - $16,336
Council requirements:
Bushfire Regulations - Inc ($4,025)
Temp fencing - Inc
Part B Termite Treatment - Inc
Sediment control - Inc
Crushed rock - Inc
Temporary Timber Crossover - Inc
SUBTOTAL - $7,394
Guidelines:
NBNCo - $2,077
Rescode Compliant Windows - $950
450mm eaves to home (garage on DBL) - $330
Provide Washing machine stop to Laundry, connected to Recycled water - $260
Recycled Water - $2,438
SUBTOTAL - $6,055
Sales说那个council bushfire regulation $4025 到时候会返还给我们的,不知道为什么要这样?
Rescode Compliant Windows 我问了能不能换成贴膜,他说不行,因为还是可以看得到外面。。。晕,到时候tender再问问
悲剧的developer requirements。。。不太清楚所谓的recycled water是什么样的water。。
更悲剧的是光site cost就$16k了,我跟sales complain太高了,直接复制email吧:
A: 'ok, to be honest I'm shocked looking at this price. Could you give me a copy of the soil test?'
N: 'We definitely can as soon as it comes in. You can choose to treat it as an order job instead of a fixed package job also. Can I ask what you were hoping the costs to come out at? Just so I can give some feedback to the house and land department.'
A: 'I have been told by the developer that they'll be doing all the benching, cut&fill, retaining wall and other works etc, the land will come in flat. My expectation would be around the $10K mark and maybe $1-2K more but definitely not $16K. Please keep me updated.'
N: 'I have checked up with the team and I have an answer. As the block is excavated and compacted they have added 9k worth of piers to the site costs. The issue they have is if the fill is engineered correctly or not. As we have no documentation on this they have to assume the worst. However if you were to treat this as an order job as opposed to fixed then there is potential for a site costs of 6-7k.
I also checked up on the rescode windows and they need to be obscured. If tinted they may not get ticked off for a permit by council as you can still see through them.'
看来site cost还是有机会可以降低的。。。上天保佑australand does a good job吧。。
|
|