我义无反顾的跳进了建房的大坑(NSW)

2013-11-21 22:45| 发布者: wyatt | 查看: 481324| 原文链接

开个贴记录一下建房的路程

看了几个月的房子,转战lower/upper north shore, st ives, west pennant hills... 始终找不到自己满意的,当然也是budget有限. 后来发现身边的朋友都在盖房子,虽然省不到钱,但至少房型可以选个自己喜欢的,也是个不错的选择.于是我们一边留意我们的dream house,一边寻找推倒重盖的地.终于,有一天机会来了,地挺平,挺方正,有700平,walk distance to school and train station,符合我们的大部分需求,果断拿下,从此义无反顾的开始了建房之路.

对了,大家要多鼓励多支持呀..我的意思,你懂的..
-----------------------------------------------------------------------------------------------------------------------------
01/12/13 - Deposit with M and C
09/12/13 - Old House Settlement
13/01/14 - Tender Appointment with M and C
20/01/14 - Tree Remove Application to Council
21/01/14 - Accept Tender (M)
21/01/14 - Give notice to tenant
07/02/14 - Council Approved for Tree Removal
12/02/14 - Contract Appointment and External color selection
12/02/14 - Sign the CONTRACT (M)
19/02/14 - 5% Deposit
27/02/14 - Contract Variation 1
28/02/14 - Section 149 Application to Council
04/03/14 - Section 149 Received
27/03/14 - Confirm Demolition with Democorp
27/03/14 - Start CDC process for Demolition
09/04/14 - Internal color selection and electrical appointment
11/04/14 - CDC preparation completed (5 weeks)
13/04/14 - Tenant moved out
14/04/14 - Requested gas meter removal (Energy Australia)
15/04/14 - Tree Removal & CDC lodged
16/04/14 - Demolition CDC Approved
17/04/14 - Gas meter removed (3 days)
23/04/14 - BASIX variation
24/04/14 - Color variation 1
05/05/14 - Give demolition notification to neighbours and council (At least 5 working days before start)
05/05/14 - Color variation 2
08/05/14 - CDC Approved
12/05/14 - Color Quote and Schedule Signed
14/05/14 - Demolition (5 days)
15/05/14 - Color Variation Signed/ Final Drawing Started
30/05/14 - Final Drawing completed
10/06/14 - Site/Construction Start
19/06/14 - Slab Completed
11/07/14 - Frame Completed
19/07/14 - Tile Selection Appointment (Di Lorenzo)
23/07/14 - Brickwork Start
14/08/14 - Roof Tile Completed for first floor
04/09/14 - Tile Selection Finalized
10/09/14 - Brickwork Completed
29/09/14 - Roof Tile Completed for ground floor
29/09/14 - Electrical Rough In Completed
03/10/14 - Gyprock Start
09/10/14 - Gyprock Completed
10/10/14 - Lock Up Stage Completed
16/10/14 - Fixing Stage Completed
17/10/14 - Final Stage Started
27/10/14 - Wet Area Tiling Started
15/11/14 - Wet Area Tiling Completed
17/11/14 - Painting Completed
05/12/14 - PCI
18/12/14 - Handover
-----------------------------------------------------------------------------------------------------------------------------
Wisdom Estimation - Manhattan 44
Manhattan 44 - Upgrade price
Eden Brae - Cremorne 41 price
Metricon Nolan 41 Pre Tender Estimation
Metricon Nolan 41 Kingston vs. Chateau
Metricon Variation Price
Sherwood 42 Pre Tender Estimation
Clarendon Color Studio - 多图
Allcastle Palace Regent 12 Variation price
DAIKIN Capacity
ActronAir Capacity
Sarking to roof and walls
Demo注意事项
Brick Mortar Types
TFO
M Tender Appointment
M Floor Covering Price
Brick Selection
M Sound Proof between Floors Price
Demolition Quote - Home Force
Things Included in Demolition Quote
Demolition Quote - Democorp
Demolition Quote - City Civil
Contract Appointment
External Color Selection
Gas Meter Removal
Color Selection
Electrical Selection
Color Quote 1
Color Quote 2
Color Selection Process
All About Demolition
Final Drawing
Construction Forecast
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Tile Selection
Week 7
Week 8
Week 9
Week 10
Week 11
Week 12
Week 13
Week 14
Week 15
Week 16
有关铺网线
Week 17
Week 21
Week 22
Week 23
Week 24
Week 25
Week 26
Week 27
Handover
大结局
-----------------------------------------------------------------------------------------------------------------------------
Total working days - 126
Rain delays - 11 Days
Public Holiday - 2 Days