开个贴记录一下建房的路程 看了几个月的房子,转战lower/upper north shore, st ives, west pennant hills... 始终找不到自己满意的,当然也是budget有限. 后来发现身边的朋友都在盖房子,虽然省不到钱,但至少房型可以选个自己喜欢的,也是个不错的选择.于是我们一边留意我们的dream house,一边寻找推倒重盖的地.终于,有一天机会来了,地挺平,挺方正,有700平,walk distance to school and train station,符合我们的大部分需求,果断拿下,从此义无反顾的开始了建房之路. 对了,大家要多鼓励多支持呀..我的意思,你懂的.. ----------------------------------------------------------------------------------------------------------------------------- 01/12/13 - Deposit with M and C 09/12/13 - Old House Settlement 13/01/14 - Tender Appointment with M and C 20/01/14 - Tree Remove Application to Council 21/01/14 - Accept Tender (M) 21/01/14 - Give notice to tenant 07/02/14 - Council Approved for Tree Removal 12/02/14 - Contract Appointment and External color selection 12/02/14 - Sign the CONTRACT (M) 19/02/14 - 5% Deposit 27/02/14 - Contract Variation 1 28/02/14 - Section 149 Application to Council 04/03/14 - Section 149 Received 27/03/14 - Confirm Demolition with Democorp 27/03/14 - Start CDC process for Demolition 09/04/14 - Internal color selection and electrical appointment 11/04/14 - CDC preparation completed (5 weeks) 13/04/14 - Tenant moved out 14/04/14 - Requested gas meter removal (Energy Australia) 15/04/14 - Tree Removal & CDC lodged 16/04/14 - Demolition CDC Approved 17/04/14 - Gas meter removed (3 days) 23/04/14 - BASIX variation 24/04/14 - Color variation 1 05/05/14 - Give demolition notification to neighbours and council (At least 5 working days before start) 05/05/14 - Color variation 2 08/05/14 - CDC Approved 12/05/14 - Color Quote and Schedule Signed 14/05/14 - Demolition (5 days) 15/05/14 - Color Variation Signed/ Final Drawing Started 30/05/14 - Final Drawing completed 10/06/14 - Site/Construction Start 19/06/14 - Slab Completed 11/07/14 - Frame Completed 19/07/14 - Tile Selection Appointment (Di Lorenzo) 23/07/14 - Brickwork Start 14/08/14 - Roof Tile Completed for first floor 04/09/14 - Tile Selection Finalized 10/09/14 - Brickwork Completed 29/09/14 - Roof Tile Completed for ground floor 29/09/14 - Electrical Rough In Completed 03/10/14 - Gyprock Start 09/10/14 - Gyprock Completed 10/10/14 - Lock Up Stage Completed 16/10/14 - Fixing Stage Completed 17/10/14 - Final Stage Started 27/10/14 - Wet Area Tiling Started 15/11/14 - Wet Area Tiling Completed 17/11/14 - Painting Completed 05/12/14 - PCI 18/12/14 - Handover ----------------------------------------------------------------------------------------------------------------------------- Wisdom Estimation - Manhattan 44 Manhattan 44 - Upgrade price Eden Brae - Cremorne 41 price Metricon Nolan 41 Pre Tender Estimation Metricon Nolan 41 Kingston vs. Chateau Metricon Variation Price Sherwood 42 Pre Tender Estimation Clarendon Color Studio - 多图 Allcastle Palace Regent 12 Variation price DAIKIN Capacity ActronAir Capacity Sarking to roof and walls Demo注意事项 Brick Mortar Types TFO M Tender Appointment M Floor Covering Price Brick Selection M Sound Proof between Floors Price Demolition Quote - Home Force Things Included in Demolition Quote Demolition Quote - Democorp Demolition Quote - City Civil Contract Appointment External Color Selection Gas Meter Removal Color Selection Electrical Selection Color Quote 1 Color Quote 2 Color Selection Process All About Demolition Final Drawing Construction Forecast Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Tile Selection Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 有关铺网线 Week 17 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Handover 大结局 ----------------------------------------------------------------------------------------------------------------------------- Total working days - 126 Rain delays - 11 Days Public Holiday - 2 Days |